Completed logistics services, customs clearance, safe and on schedule less than 60 days inland transportation for the Cu Ne 1&2 and Krong-Buk 1&2 wind farm projects.
Performance Services:
Project: Cu Ne 2 Wind power – Krong-Buk district, Dak Lak province.
Road transport route:
From Ba Son port for wind blades to site, distance 480 km.
From South Van Phong port for main heavy components, distance 240 km.
Volume: 19 sets wind turbine equipment, 50MW generating capacity.
Time performance:
Start: October 2023
Finish: December 2023