CU NE 1&2 AND KRONG-BUK 1&2 WIND FARM TRANSPORT PROJECTS

Completed logistics services, customs clearance, safe and on schedule less than 60 days inland transportation for the Cu Ne 1&2 and Krong-Buk 1&2 wind farm projects.

Performance Services:

Project: Cu Ne 2 Wind power – Krong-Buk district, Dak Lak province.

Road transport route:

From Ba Son port for wind blades to site, distance 480 km.

From South Van Phong port for main heavy components, distance 240 km.

Volume: 19 sets wind turbine equipment, 50MW generating capacity.

Time performance:

Start: October 2023

Finish: December 2023

Contact our operation experts for further information

Our team is ready to answer any question that you may have

NEW WORLD LOGISTICS J/S COMPANY
HEAVY LIFT - MEGA MOVES & PROJECT CARGOES
An exclusive partner in Vietnam of 

OEG ASIA PACIFIC LTE LTD.,

ISO 9001:2015; 14001:2015 & 45001:2018

Add: 4th floor, Vietcombank Building, 21 Le Thanh Phuong,
  Nha Trang City, Khanh Hoa Province, Vietnam.
+(84)-2583 820 656
+(84)-2583 820 657
sales@newworldlogistics.vn; brandon@newworldlogistics.vn
www.newworldlogistics.vn

Copyright @2003 New World Logistics JSC. All rights reserved.

                                                                                   Membership of:

    

visitor
709858